It was a sweltering 39 degree weather when I went yesterday, but it was really cool inside the house even without the window covers and trees and plants yet. Our Hebel and double glazed windows costs have paid off really well.
I didn't go up the first floor anymore, I'll just wait for our stairs to be installed before I try again :-) Now that our SS is back from his holiday, we are expecting more action in our place. He mentioned stairs, doors, cabinets, tiles fixing and paint will be started end of this month :-)
We are going on holiday next week until first week of February and once we come back, we start ordering and booking our flooring and carpet and window covers. We also need to plan our driveway and concrete skirting, landscaping, post box and clothes line.