Wednesday 1 November 2017

Day 80 of 266

We had our frame re-inspection and pre-plaster inspection today. Out of the 13 issues noted during our frame inspection, 7 were still outstanding. One of these was the bony edge to our slab which we are still waiting for PD engineering report and the other one is the uneven section section of the slab which our SS said will be attended to prior to hand-over. All the other 5 outstanding issues were related to  frame.

Based on the latest inspection report, there are now 22 noted defects which include the 7 outstanding defects from frame re-inspection.

Our Hebel installation also started today. I was assured by the installer that they were instructed to leave the front slab with issue alone.

Our Hebel Installation

   


Our Pre-plaster Inspection
(The blue spray paints were from pre-plaster inspection and the red ones were the slab and frame inspection)

The Ground Floor





 

   