Based on the latest inspection report, there are now 22 noted defects which include the 7 outstanding defects from frame re-inspection.
Our Hebel installation also started today. I was assured by the installer that they were instructed to leave the front slab with issue alone.
Our Hebel Installation
Our Pre-plaster Inspection
(The blue spray paints were from pre-plaster inspection and the red ones were the slab and frame inspection)
The Ground Floor
The First Floor